Farmington Hills Water Supply System Improvements, Phase II, Contract No. 3-Water Storage Tank Site Work
Oakland County, MichiganWater Resources CommissionerFarmington Hills Water Supply System Improvements, Phase II, Contract No. 3-Water Storage Tank Site Work

Farmington Hills Water Supply System Improvements, Phase II, Contract No. 3-Water Storage Tank Site Work

The project consists of site grading, pavement replacement, storm drainage improvements, cell tower demolition, and the construction of a materials storage structure. Bids for the project were received on July 23, 2014 and the construction contract was awarded to Adamo Demolition Company of Detroit, Michigan for their low bid amount of $1,159,082.60. Work began in August, 2014 and the project is scheduled to be completed in the spring of 2015. George Nichols, P.E., is the WRC project engineer assigned to the project. OHM Advisors, Inc. in the design engineer